Rail Obstacle Deflector

Manufactured to the EN 15085 CL2 railway welding standard. Heavy plate assembly welded with full traceability. Post-weld full machining ensures accurate mounting surfaces and holes to satisfy vehicle assembly geometric tolerances. Complete anti-corrosion coating after machining, meeting adhesion, impact and salt spray requirements for rail outdoor service, showing Fengshi's expertise in large welded rail structural parts.

Manufacturing route: 7 processes in-house

  1. 01Laser CuttingCut
  2. 02Pressing & BendingForm
  3. 03WeldingJoin
  4. 04CNC Machining CenterMachine
  5. 05Surface TreatmentFinish
  6. 06ColouringFinish
  7. 07AssemblyIntegrate

No sub-suppliers in this chain. The part never leaves our site between step 01 and dispatch.

On the shop floor: 9 operations in this order

  1. Laser cutting
  2. bending
  3. welding
  4. PT test
  5. CNC milling
  6. sandblasting
  7. wet painting
  8. assembly
  9. packing